Exelon Warehouse

Corrado American provided construction site services including:

  • Site demolition of paving and concrete
  • Excavation and installation of domestic water services
  • Excavation and installation of sanitary sewer
  • Excavation and installation of electrical duct banks
  • Building concrete footers and slab for 7,000 square foot warehouse
  • Storm drainage improvements including installation of bio retention pond for improved storm water quality
  • Installation of concrete curbs and sidewalks
  • Asphalt paving and striping

Key Challenges

Removal of rock within the building foot print.

Project Details

Project:Exelon Warehouse

Client:Exelon

Location:Darlington, Maryland

Classification:Industrial

Job Size:Under $1 Million