Westtown Elementary
Project Scope Earthwork, utilities, and parking lot for a new school addition, plus foundations and slab for the new addition. Earthwork: 2,000 CY Utilities: 300 LF Paving: 350 Tons Concrete: 7300 SF Curb: 450 LF Sidewalk: 140 LF Key Challenges Space was a major challenge on this project due Continue reading